- Send part number, alternates, condition accepted, documents required and location.
- Ask several suppliers in parallel; AOG desks work around the clock.
- Compare total time to the aircraft, not only the quoted price.
- Never relax document checks, even under time pressure.
What to send
- Part number and acceptable alternates or interchangeable part numbers.
- Conditions accepted: new, overhauled, serviceable.
- Release certificates required: EASA Form 1, FAA 8130-3 or dual.
- Aircraft registration, location and the airport of delivery.
- Whether an exchange or outright purchase is acceptable.
Reach suppliers in parallel
Major distributors, used serviceable material specialists and MRO providers run AOG desks. Asking several of them at once, with complete data, returns offers within hours. Asking one at a time can cost a day.
Compare time to the aircraft
| Factor | Question |
|---|---|
| Location of stock | Where is the part now? |
| Shipping | Courier, next flight out or hand carry? |
| Customs | Can it clear quickly at destination? |
| Documents | Are certificates ready to send before shipment? |
After the event
Record what happened: which supplier answered first, the price paid and the total time to the aircraft. That history turns the next AOG into a faster decision.
Partvoya and aviation
Partvoya’s procurement engine asks the right suppliers in parallel and keeps every price on record. Aviation operators can join the waiting list or see the aviation supplier directory.
Questions
What does AOG mean?
Aircraft on ground: an aircraft that cannot fly until a part is replaced or a repair is completed.
Should document checks be skipped to save time?
No. A part without valid paperwork cannot be installed, so incomplete documents cost more time, not less.