- Rank equipment by the cost of its failure, not by the price of its parts.
- Keep critical, long-lead parts on site; source the rest when needed.
- Watch for obsolescence notices before a part becomes unavailable.
- Review stock levels with real usage and price history each year.
Rank by consequence
Start with the equipment, not the parts. For each machine, ask what a failure would cost: lost production per hour, safety and environmental impact, and whether a standby unit exists. Equipment with high consequences and no redundancy is critical; its key spares deserve attention first.
Combine criticality and lead time
| Short lead time | Long lead time | |
|---|---|---|
| Critical | Keep a minimum on site | Keep on site; agree supply with a backup source |
| Non-critical | Buy when needed | Plan ahead from running hours and inspections |
Plan for obsolescence
Makers announce the end of production for drives, PLCs and electronic modules. When a notice arrives, decide early: buy a last-time stock, qualify an alternative or plan an upgrade. Suppliers that specialise in discontinued automation parts can bridge the gap, but prices rise as stocks fall.
Review with real data
Once a year, compare stock with actual usage. Parts never used in five years may be reduced; parts bought urgently more than once may need a minimum stock. Price history shows which suppliers were reliable and which prices have drifted.
How Partvoya helps
Partvoya keeps every requisition, quote and price in one place, so usage and price trends are visible without spreadsheets. Industrial buyers can request early access.
Questions
What is a critical spare?
A part whose absence would stop critical equipment for longer than the business can accept, usually because its lead time is long.
How often should spares stock be reviewed?
At least once a year, and after any major failure or equipment change.